Name: UPPER CLAYHILL SOLAR FARM
Project details: 4.75MWp Ground Mounted System
The park, built in the town of Lewes, in the East Sussex County during the 2015 using a ground mounted system, delivers a power of 4.75MWp.
Renergy Power Plants was commissioned of the sub-contracting management, delivering the complete construction, civil, mechanical and electrical, proven by cold commissioning test, of the park, managing the materials supply and the logistic of the site.
SCOPE OF WORK:
- Civil, Mechanical and Electrical Installation
- Sub-Contracting management
- Cold Commissioning